Company Active LTD

Company profile

Cable Coatings Limited

Thermal Metaphotonics - AssetCool

Cable Coatings Limited is a UK company with status active founded in 2016 based in Yorkshire and the Humber.

CRN
10096075
Founded
2016
Age
10

Overview

Legal name
CABLE COATINGS LIMITED
Region
Yorkshire and the Humber
Registered address
TERAWATT ONE UNIT A1
GRANGE VALLEY ROAD
BATLEY
WEST YORKSHIRE
ENGLAND
WF17 6GH
Insolvency history
No

Corporate ownership

Updated 06 Jun 2026 16:52

Cable Coatings Limited
No active corporate controller recorded.

Latest accounts

Financial period: 1 May 2024 to 30 Apr 2025

FULLACCOUNTS
Turnover
Unknown
Profit / Loss
Unknown
Employees
17

Company events

Reference milestones and recent Companies House filing stream events.

6 events
31 Jan
2027

Accounts due

Accounts Due

Next accounts due date

18 Oct
2026

Confirmation statement due

Confirmation Due

Next confirmation statement due date

04 Oct
2025

Confirmation statement filed

Confirmation

Last confirmation statement made up date

30 Apr
2025

Accounts filed

Accounts

Last accounts made up date

13 Nov
2024

Confirmation Statement With No Updates

Confirmation-statement

CS01 | Transaction MzQ0MzAzNzY4NmFkaXF6a2N4

Published 13 Nov 2024 10:26

01 Apr
2016

Incorporated

Inception

Company registered at Companies House

Public funding

5 awards
First funded
2017
Funded years
2017, 2019, 2022, 2024
Age at first award
1 years

Projects

2024 Collaborative R&D Lead participant

JCR: Retrofit application of spectrally selective coatings for transmission line jumper conductors

1 Oct 2024 to 31 Mar 2026

Awarded
£347,516
Total cost £496,452

The current carrying capacity of overhead transmission, and distribution (T+D) lines has become a key constraint for global electrification. Global electricity demand is due to increase 75-150% 2022-2050 (IEA,2022). The current mechanisms to increase T+D capacity are based on large infrastructure projects such as reconductoring, taking 3-7 years, costing ...

2024 Collaborative R&D Lead participant

RASSCOL Nepal: Retrofit Application of Spectrally Selective Coatings to Overhead Lines

1 Jun 2024 to 31 Aug 2025

Awarded
£310,743
Total cost £443,918

The project aims to demonstrate discontinuous cost savings in upgrading transmission and distribution capacity via the application of capacity-enhancing coatings to overhead lines.

2022 Collaborative R&D Lead participant

Novel application technology for retrofit application of spectrally selective coatings to overhead transmission and distribution lines

1 Oct 2022 to 31 Dec 2023

Awarded
£299,549
Total cost £427,927

Feasibility study of autonomous coating solutions for the purposes of modifying surfaces of transmission infrastructure.

2019 Collaborative R&D Lead participant

Spectrally Selective Coatings to Increase Transmission Network Capacity

1 Nov 2019 to 31 Jul 2021

Awarded
£259,930
Total cost £371,329

Please describe your project. This description will be published only if your project is subsequently funded by Innovate UK to comply with government requirements. Providing this summary is mandatory but the text will not be assessed. Please ensure it is suitable for public disclosure. Funding will not be provided to successful projects without this.

2017 Feasibility Studies Lead participant

Low Cost Method to Boost Grid Capacity: A Feasibility Study

1 Nov 2017 to 31 Oct 2018

Awarded
£137,200
Total cost £196,000

Novel low cost power cable coating to boost electrical grid capacity.

Product types

Collaborative R&D Feasibility Studies